Supply of Mineral Rights
An Iron Mine fully transfer project

Shanghai International Mining Exchange

Project Information
Project No.   20170710383140
Project Name   An Iron Mine fully transfer project
Project Classification Property rights of mining companies
Location   Shandong/ China
Minerals   Iron
Project Information Mining area   0.1619 square kilometers
Reserves/grade   

(332+333) ore extent:4,774,000t,

TFe average grade:20.12%,

mFe average grade:10.05%

332: 1,838,200t;

333: 273,300t

Mining method   Underground mining
Supporting facilities   
Others

The terrain is flat, with the elevation of 3.3m-4.4m above sea level, and under continental temperate continental climate. The annual average temperature is 12.2 degrees and the annual average precipitation is 654m, mainly in the period from June to August. The west side of the mining area is near Jialai Bay, with the width of 200m-400m. The local advanced economy meets the supply of  electricity and labor

 

The main ore of this mineral ore is magnetite, with a small amount of ilmenite, pyrite, and chalcopyrite. The gangue minerals are mainly amphibole, pyroxene, plagioclase, apatite, quartz, lacquered stone, and calcite. The average grade of TFe in ore is 20.12%, with the average mFe of 10.05% and the ratio of mFe / TFe of 50.5%, and thus it is categorized as low grade and weak magnetic ore. The main slagging component is CaO + MgOmFe, with an average of 10.05%, and mFe / TFe ratio of 50.5%, which is categorized as low grade and weak magnetic ore. The ratio of CaO + MgO / SiO2 + Al2O3 is 0.31%, which belongs to acidic ore. The content of harmful components in the ore, S with 0.37% -0.64% and P with 0.014% -0.26%, has no effect on the quality of the ore. No associated beneficial components were found in the ore for comprehensive utilization.

 

A total of 7 ore bodies were found (I-1, I-2, I-3, I-4, I-5, II-1 and II-2), and the ore bodies were lenticular. It is produced in Jingshan wild group. The shape of production and the stratum is basically the same: the northwest - North East, tends to North East - South East, with the inclination of 180-530 angle. Ore bodies are not exposed to the surface, which is the blind ore body. The I-1, I-2, I-3, and II-1 ore bodies are larger and the other ore bodies are smaller.

 

 

Ore body

Distribution

Drillings

Length (m)

Maximum slant depth(m)

Elevation

(m)

Thickness

(m)

Average thickness

(m)

I-1

11∽19 lines

7

400

174

-35.9∽-213.5

1.35∽14.12

6.22

I-2

11∽19 lines

7

400

 

-45.9∽-283.3

1.56∽10.77

6.39

I-3

13∽19 lines

6

300

 

-57.8∽-253.6

1.02∽16.69

7.40

II-1

0∽7

lines

5

320

 

-91.7∽-203.4

1.01∽16.53

5.51

 

 

 

 

Ore body

Thickness coefficient of variation

Thickness

level

 TFe

grade

Average

 

Grade coefficientof variation

I-1

14%

Stable

17.38%∽23.18%

20.28%,

15%

I-2

30%

Stable

17.73%∽22.37%

19.43%

22%

I-3

37%

Stable

17.32%∽22.32%

20.20%

3%

II-1

16%

Stable

17.87%∽25.69%

20.89%

17%

 

 

 

Ore body

mFe

grade

Average

Grade coefficientof variation

Grade

level

Others

I-1

8.66%∽13.68%

9.88%

25%

even

I layer stone;

Inner structure simplex

I-2

 

 

 

even

I layer stone;

Inner structure simplex

I-3

9.14%∽10.03%

9.55%

14%

even

No  stone;

Inner structure simplex

II-1

8.27%∽15.97%

10.98%

31%

even

I layer stone

Inner structure simplex

Progress   A 1: 10000 high-precision magnetic profile of 37.8km was carried out from 2002 to 2003 in this area. In 2004, three boreholes were constructed, the magnetic anomalies were verified, and the iron ore survey was submitted. The work on the basis of previous work, began in February 2007, and ended in April 2008. Take a drilling as the main approach to control the ore body, the main physical workload by now are flowing: 1: 10000 Geological testing 4.12 km2; 1: 2000 terrain geological survey 1.66km2; 1: 5000 high-definition magnetic measurement 1.75km2; 1: 2000 high-precision magnetic measurement 4.12km2; 1: 5000 magnetic profile 37.8km; electrical joint section 3.85km; geological drilling 3935.05m / 18 holes; hydrogeological drilling 516.10 / 2 hole; borehole pumping experiment 2 holes; civil wells survey 26 cases; 184 samples for basic analysis; 1 for complete analysis; 8 for the combination, the experimental class 10/30, 14 for analysis of water quality, other types of samples tested 133. The deposit is of the type III survey, and the amount of resources is estimated from the construction distance of 100m (332). Due to low ore grade, according to the requirements of Provincial and Ministerial Office, Provincial Review Office organized the experts of mineral industry to demonstrate the industrial indicators, all agreed to use industrial indicators (Lu Guo land-resource file [2008] 04): Boundary grade mFe ≥ 8%, the lowest industrial grade mFe ≥ 9%, the minimum recoverable thickness of 1m, clip stone removal thickness of 2 meters, with the geological block method in the horizontal projection map to estimate the amount of resources. The project has obtained the mining permit, all licenses are completed.
Cooperation   Fully transfer, no liability
Keywords   
Listing   
Quoted Price   80,000,000 RMB
Deadline   2017.07.25-2018.07.24
Address    Zip Code   
Name   Eric Wang Website   www.shumx.com
Telephone   +86-21-66283339 Fax   
Mobile phone    E-mail   ericwang@shumx.com